Massachusetts School Building Authority

MURSD has been accepted into the MSBA Accelerated Repair Program

The MSBA is a state authority that partners with Massachusetts communities to support school building projects. For MURSD specifically:

  1. Initial Steps:

  • In Spring 2023, MURSD submitted a Statement of Interest to the MSBA for their Accelerated Repair Program (ARP)

  • The school district was one of 70 proposals from 37 districts across Massachusetts to be considered

  1. Project Approval:

  • In October 2024, MURSD was accepted into the MSBA Accelerated Repair Program specifically for the Nipmuc Roof project

  • This program focuses on energy-efficient and cost-saving upgrades that will result in direct operational savings

  1. Current Status:

  • December 2024: MURSD approved funding for roof schematic design and formed a building committee

  • January 2025: The district submitted additional information to MSBA

  • The project must be treated as a stand-alone warrant item, separate from the broader capital projects.

  1. Financial Impact:

  • While the district must request the full amount under the debt exclusion, the MSBA will provide significant reimbursement for the Nipmuc roof repair costs

  • This reimbursement will substantially reduce the final amount the district needs to borrow

MSBA Process

MURSD has completed Module 1 and Module 2. We have been assigned an OPM and design team and we are in the Module 4 step.

msba